Before anything starts

Six things have to be settled first, and not all of them are ours

Most jobs that run late run late on this list rather than on the work itself. Each line says who owns it.

  1. 01

    Tank decommissioning and cleaning

    Who Specialist contractor, before we start

    Tanks emptied, cleaned, degassed and certified gas free. This is the step everything else waits on and it is not demolition work.

  2. 02

    Environmental site assessment

    Who You, through a consultant

    What is in the ground around the tanks decides the disposal classification and therefore most of the cost.

  3. 03

    Regulatory notification

    Who You and your consultant, with the relevant authority

    Removing underground petroleum storage systems is a notifiable activity with its own requirements, separate from the demolition approval.

  4. 04

    Hazardous materials survey

    Who Max, through an accredited laboratory

    The shop and canopy still need surveying for asbestos like any other commercial building.

  5. 05

    Service disconnection

    Who You, with each authority

    Power, water and any remaining gas supply.

  6. 06

    Validation plan

    Who You, through your consultant

    How the site will be shown to be clean once the tanks are out. Agreeing this before excavation starts is what stops the hole staying open.

Scope

What the quote does and does not cover

Stated side by side so there is nothing to discover later. Anything in the right hand column can be added, it is simply priced separately.

Included as standard

ItemWhat that means
Canopy, shop and forecourtThe visible structures, including signage and pump islands
Tank excavation and removalOnce the tanks are certified gas free by the specialist
Pipework and linesFill lines, vent lines and the associated in ground pipework
Excavation around the tanksTo the extent the validation plan requires
Separation and cartageMaterial separated and carted to the right destination
Asbestos managementSurvey, licensed removal, clearance and licensed disposal

Quoted separately

ItemWhy it is separate
Tank cleaning, degassing and gas free certificationSpecialist contractor work, before demolition
Environmental assessment and validationConsultant work, before and after
Contaminated soil disposalClassified first, then priced on the classification
Groundwater treatmentA separate scope with its own approvals
Backfill and compactionQuoted separately once the validated extent is known
Remediation beyond the tank pitPriced when the assessment says how far it goes

The detail

Why the tanks decide everything

  • Nothing happens until they are gas free. Tanks have to be emptied, cleaned, degassed and certified by a specialist before any machine goes near them. That certificate is the gate.
  • The hole is bigger than the tanks. Excavation goes as far as the validation plan requires, and that extent is set by the assessment rather than by the tank dimensions.
  • The soil classification is the price. Hydrocarbon affected soil goes to a facility licensed for it. The volume and the classification together are usually the largest line on the job.
  • The hole cannot be closed until it is validated. Backfilling before the consultant has taken their samples means digging it out again.
  • Water finds the pit. An open excavation at a fuel site collects water, and that water is usually classified too.
  • The paperwork outlives the job. The validation report is what a future purchaser or certifier asks for. It is worth getting right the first time.

What we need to quote it

The address
So we can look at access and what is around it
Photographs
One from the street and one of the work itself
Any reports you hold
Hazardous materials, structural, survey or levels
Your dates
What has to be finished by when, and what is waiting on it

We attend the site before quoting anything substantial.

The soil, not the structure, is the number to watch

Hydrocarbon affected ground is classified before it can be priced, and the classification decides where it can go. We price the excavation and cartage on rates agreed in advance rather than a fixed figure, so the exposure is visible.

Land Remediation

Before you book

What people ask about this one

Do you remove the underground tanks yourselves?
We excavate and remove them once a specialist contractor has emptied, cleaned, degassed and certified them gas free. That certification is not demolition work and we do not do it. What we do is coordinate the sequence so the two halves line up.
How much of the forecourt has to come out?
As far as the validation plan says, which comes from the environmental assessment rather than from us. That is why the assessment is worth doing before the quote rather than after.
Can you give a fixed price?
For the structures, yes. For the excavation and the soil disposal, not honestly, until the ground is classified. Those are priced on rates agreed before we start, so the exposure is visible rather than hidden in a contingency.
What if contamination goes beyond the site boundary?
That becomes a matter for your consultant and the relevant authority, and it is outside what a demolition contract can resolve. It is also a reason to assess before committing to a date.
How long does a service station take?
The structures are quick. The tank removal, the excavation, the validation sampling and the backfill are what make it a programme rather than a job, and the consultant’s turnaround on the samples is part of it.

Get a quote

Send the site and the assessment if you have one

The address, the number and size of the tanks, and the environmental assessment if one exists. The assessment is what turns a range into a price on this kind of site.

  • Structures priced fixed, soil and excavation priced on agreed rates
  • Sequenced around the specialist tank contractor and your consultant
  • Classified soil to a facility licensed for that classification
Prefer to talk 0456 220 552

Special demolition offer

Get your free demolition quote

Demolition and removal services from $15,999*. Tell us about your project and we'll help you understand the costs.

*Starting price applies to eligible demolition and removal projects only. Final pricing depends on structure size, materials, site access, location, waste disposal requirements, hazardous materials and any necessary approvals. A final quote will be provided following project assessment.

Or call 0456 220 552 during business hours, or use the full quote request form.

Call Now