Knocking down your own house

Most people do this once. The things that change the price are not obvious from the street, the longest item is never the demolition itself, and the quotes you are comparing are probably not comparing the same job. Here is how it actually runs.

0456 220 552

How it runs

Five stages, and only one of them is the demolition

The order matters more than the speed. Anything hazardous comes out and is cleared before the structure is touched.

  1. 01

    Before you commit to anything

    Find out what is actually on the block

    The things that change a demolition price are almost all invisible from the street: asbestos in the eaves or the wet areas, a pool nobody counted, rock close to the surface, a shared boundary structure, or a side gap too narrow for a machine. A site visit settles all of them, and it costs you nothing to have one before you sign anything.

  2. 02

    While you are comparing quotes

    Check what each price actually includes

    Demolition quotes are rarely comparable as written. Ask each one whether asbestos removal and independent clearance are inside the price, whether the slab and footings come out, whether the pool is included, and who pays if the spoil is classified as contaminated. A cheap number with four exclusions is not a cheap job.

  3. 03

    Approval and disconnections

    The part that takes the longest

    Water, sewer, gas, electricity and telecommunications all have to be disconnected and confirmed in writing before anything comes down, and those bookings sit with the authorities rather than with us. They are started the day approval lands. If anyone tells you demolition can begin without them, that is a reason to walk away.

  4. 04

    The week itself

    What happens on site, and what the neighbours see

    Anything hazardous comes out first and is independently cleared before the structure is touched. Then the building comes down with the material sorted as it falls, water used for dust, and the work kept inside the hours the approval sets. We will tell you which days are loudest so you can let the neighbours know rather than have them find out.

  5. 05

    Handover

    A level, clear block and the paperwork to prove it

    The block left graded and clear, the slab out or left in place depending on what your builder needs, and the disposal dockets handed over so the waste trail is documented rather than described. If a site cut is in scope, it is finished to the level your engineer nominated.

Why it matters who holds the contract

Four trades, or one

A knockdown rebuild usually needs asbestos removal, demolition, a site cut and the cartage. Engaged separately, each one waits on the last, each one blames the one before it when the programme slips, and you are the person coordinating four sets of insurance, four invoices and four site inductions.

On one contract there is one mobilisation, one programme and one person answering the phone. The asbestos removal is still carried out by licensed asbestos removalists and the clearance is still issued by an independent licensed assessor, because that independence is the point of it. What changes is that you are not the one arranging it.

Max holds the demolition licence, AD214737, issued by SafeWork NSW. Ask any demolition contractor for their licence number before you sign. It is a public register and it takes a minute to check.

Partly demolished Sydney house with the roof framing collapsed and brick and timber debris piled across the site

What to send us

Six things, and none of them cost you anything

Send what you have. We will tell you what is missing rather than price around it.

WhatWhy it mattersIf you do not have it
The addressLets us look at the street, the frontage and the access before we come outWe visit the site before quoting anything substantial
A few photographsThe front of the house, the side gap, the rear yard and anything unusualTells us the machine size, which is most of the price
What is coming downHouse only, or the pool, shed, garage, slab and driveway as wellEach one is a separate waste stream with its own rate
Your approval or CDCWhat the consent permits and the conditions attached to itIf it is not granted yet, tell us what you have applied for
Any asbestos report you haveWhether removal is a day or a week, and under which licence classIf there is none, we arrange assessment before the quote is finalised
Your builder's requirementsSlab out or left, final level, and the date they need the blockWe quote to clear and graded at the level nominated

Straight answers

Things people are too polite to ask

How much does it cost to knock down a house?
Anyone who gives you a figure without seeing the block is guessing, and the guess will be revised. What moves the number most is the asbestos, the access and whether the slab and footings are coming out. A site visit and an hour of our time produces a price you can actually rely on.
Do I have to tell my neighbours?
Your approval conditions may require notification, and either way it is worth doing. We will tell you which days are loudest and when trucks will be in the street, so the conversation happens before the noise rather than after it.
What if asbestos is found after the quote?
That is why we arrange assessment before the quote is finalised rather than after. Where something is genuinely unforeseen, it is priced at the rates agreed up front instead of as a renegotiation.
Can I keep the pool, or the garage, or a tree?
Yes. Partial demolition is routine work. Anything retained is protected and left in a usable condition rather than simply avoided, and a protected tree has its root zone kept clear of plant and stockpiles, which affects where the machine can stand.
Does the slab have to come out?
Only if your new build needs the ground back. Sometimes a slab stays and is built over. It is much cheaper to settle this with your builder before the quote than to change it halfway through.

We work the whole corridor

Wollongong through Greater Sydney and the Central Coast to Newcastle. Western Sydney and the Northern Beaches are where we are most often.

Homeowners

Send the address and a few photographs

Tell us what is standing and what your builder needs the block to look like. We will come and look before quoting anything substantial, and we will tell you what is missing rather than price around it.

  • Asbestos, demolition, site cut and cartage quoted as one job
  • Demolition licence AD214737, issued by SafeWork NSW
  • A price based on a site visit rather than a phone call
Prefer to talk 0456 220 552

Special demolition offer

Get your free demolition quote

Demolition and removal services from $15,999*. Tell us about your project and we'll help you understand the costs.

*Starting price applies to eligible demolition and removal projects only. Final pricing depends on structure size, materials, site access, location, waste disposal requirements, hazardous materials and any necessary approvals. A final quote will be provided following project assessment.

Or call 0456 220 552 during business hours, or use the full quote request form.